Bellvue and Southeast Area Mill and Overlay
The City of Brooklyn Center’s Capital Improvement Plan identifies a potential street rehabilitation project in this neighborhood. This project is tentatively scheduled for 2019. A feasibility study will be undertaken to evaluate the need for the project and estimated cost of rehabilitating the streets and utilities.

On March 11, 2019, the City Council will consider the City Engineer's Feasibility Report and declare costs to be assessed and call for two public hearings on April 8, 2019. Property owners were mailed a letter detailing the project and special assessment information together with Notices of Public Hearings and a feasibility summary.


Project Improvements
Mill and overlay pavement with partial curb and sidewalk replacement
Storm sewer repairs
Sanitary sewer repairs
Water main repairs          


Contact Information
For all project coordination issues and information please contact:
            
     • Jay Hill, Project Manager/Inspector 
       763-569-3332 or yn-center.mn.us
           
           
Utility Outages

Please contact the following for utility outages:
 
  • CenterPoint Energy gas leak: 612-372-5050
  • Xcel Energy (electric outage): 1-800-895-1999
  • CenturyLink: 1-877-348-9007
  • Comcast: 1-800-934-6489
  • City of Brooklyn Center (water, sanitary sewer, storm sewer, street lighting or traffic signal systems) between 7:00 a.m. to 3:30 p.m. please call 763-585-7100. After hours call 911 (the dispatcher will contact the appropriate on-call service staff). 
  •                                                                                        
                                                                                                         
Project Schedules                                                                          

March 11, 2019 - City Council to receive feasibility report

March 20, 2019 - Neighborhood informational meeting

April 8, 2019 - City Council to conduct public hearing, authorize the project and order preparation of plans and specifications

April 22, 2019 - City Council to approve plans and specifications and authorize the advertisement for bids

May/June 2019 - City Council to accept bids and award contract

June/July 2019 - Start project construction


                                                




                                                



               




                                            


                                               

Bellvue SE.jpg



Project Information
Informational Meeting Invitation

Public Hearing/Assessment Notification Packet Mailed



Newsletters
July 2019
September 2019



Construction Updates
August 19, 2019
September 3, 2019
September 9, 2019
September 23, 2019
September 27, 2019
October 7, 2019
October 14, 2019