Interstate Area Street/Utility Improvements

The City of Brooklyn Center’s Capital Improvement Plan identifies a potential street reconstruction project in this neighborhood. This project is tentatively scheduled for 2019. A feasibility study will be undertaken to evaluate the need for the project and estimated cost of reconstructing the streets and utilities. A survey crew was in the neighborhood over the summer months collecting data and a meeting was held on October 24, 2018, to gather additional information and solicit input from neighborhood residents.

On November 13, 2018, the City Council accepted the City Engineer's Feasibility Report, declared costs to be assessed and called for two public hearings on December 10, 2018. Property owners will be mailed a letter detailing the project and special assessment information together with Notices of Public Hearings and a feasibility summary.    

On December 10, 2018, public hearings were held regarding ordering improvements and authorizing preparation of plans and specifications, and acceptance of the levy roll certifying special assessments. Property owners are able to pay their assessments before September 30, 2019, without interest. From October 1 through November 20, 2019, property owners may pay the assessments with interest calculated from October 1, through the date of payment. Special Assessments not paid by the end of the business day on November 20, 2019, will then roll to Hennepin County property taxes and are payable over a ten (10) year period, beginning in 2019. 
           
           
Project Details
Full street reconstruction with concrete curb and gutter
Partial Storm sewer replacement
Sanitary sewer replacement
Partial water main replacement

Contact Information
Please contact the following for all of your project coordination issues and information.

                       

Utility Outages
Please contact the following:
  • CenterPoint Energy (gas leak): 612-372-5050
  • Xcel Energy (electric outage): 1-800-895-1999
  • CenturyLink: 1-877-348-9007
  • Comcast: 1-800-934-6489
  • City of Brooklyn Center 7 am to 3:30 pm: 763-585-7100
    • Water
    • Sanitary 
    • Storm Sewer
    • Street Lighting
    • Or Traffic Signal Systems
  • After hours call 911 (the dispatcher will contact the appropriate on-call service staff)
  •            
                                                         
    Project Schedule

    October 24, 2018 - Neighborhood informational meeting held

    November 12, 2018 - City Council to receive feasibility report

    December 10, 2018 - City Council to conduct public hearing, authorize the project and order preparation of plans and specifications

    February 25, 2019 - City Council to approve plans and specifications and authorize the advertisement for bids
                   
    May 31, 2019 - Bid Opening

    June 10, 2019 - Project Award

    June 17, 2019 - Preconstruction Meeting

    June 2019 - East of Camden (Start of Construction)

    October 2019 - East of Camden (End of Construction)

    April 2020 - West of Camden (Start of Construction)

    October 2020 - West of Camden (End of Construction)
                   
                                           
                     



    Project Area Map website COMPRESSED.jpg
                     Enlarge Map

                   
    Project Information
    Informational Meeting
                   
    Informational Meeting Packet
                                
    Public Hearing/Assessment Notification Packet Mailed
                   
    May 10, 2019 Project Update Letter
                                   
                   

    Newsletters
    June 2019
    August 2019
    September 2019



    Construction Updates
    June 20, 2019
    June 26, 2019
    July 8, 2019                               
    July 15, 2019
    July 22, 2019
    July 30, 2019
    August 5, 2019
    August 19, 2019
    September 3, 2019
    September 9, 2019
    September 23, 2019
    September 27, 2019
    October 7, 2019
    October 14, 2019